Private Construction Bond Perfection, NTC & Nonpayment Notice Timetables
Under Florida Statutes § 713.23, an owner who requires the prime contractor to furnish a statutory payment bond transfers all mechanics lien liability away from the real estate and onto the surety bond. Because the property is immune from foreclosure, claimants must strictly adhere to the statutory notice prerequisites to maintain an enforceable remedy against the surety.
The 45-Day Notice to Contractor Trap: Claimants lacking direct contractual privity with the prime contractor must serve the 45-day NTC. Unlike some states where late notice merely reduces priority, in Florida, failure to serve the NTC within 45 days of commencing work completely and permanently extinguishes all rights under the payment bond.
Notice of Contest Acceleration: Under Fla. Stat. § 713.23(1)(e), a contractor or surety can shorten the standard 1-year lawsuit deadline to just 60 calendar days by recording a formal 'Notice of Contest of Payment Bond Claim' in the county clerk's office and serving it on the claimant. Failure to file suit within 60 days of service discharges the surety automatically.