Florida Statutes · Chapter 713 Construction Lien Law

Florida Statutes § 713.06 Notice to Owner (NTO) 45-Day & Improper Payment Auditor

Audit Florida statutory Notice to Owner (NTO) 45-day service cutoffs under Fla. Stat. § 713.06, enforce the 40-day certified mailing safe harbor under § 713.18, and calculate owner improper payment exposure under § 713.06(3).

1. Lienor Service & Contract Inputs

Commences strict 45-calendar-day NTO statutory service countdown.
Fla. Stat. § 713.18 provides date-of-mailing protection ONLY if mailed within 40 days.
Funds paid to contractor without obtaining lien waiver from NTO lienor are improper payments.

Florida Statutory Conditions Checklist:

2. Statutory Deadlines & Owner Exposure

Strict 45-Day NTO Statutory Cutoff
Calculating...
NTO TIMELY SERVED
Owner Improper Payment Exposure (§ 713.06(3))
$65,000 Exposure

Owner disbursed $110,000 to contractor after NTO service without obtaining lien release.

Section 713.08 Claim of Lien 90-Day Recording Deadline
Calculating...

Must record claim of lien within 90 days of last furnishing in county records.

Florida Construction Lien Law Synthesis:
Under Fla. Stat. § 713.06(2)(a), service of the NTO within 45 days is a strict condition precedent to lien validity. If the owner continues to pay the direct contractor without securing releases from NTO holders, payments are deemed improper under § 713.06(3), leaving property subject to double payment exposure.

Florida Practice Recommendations:

  • Owner must require statutory progress lien releases (§ 713.20) from all NTO lienors prior to each draw.
  • Never disburse final contract retainage without receiving the Final Contractor Payment Affidavit.
  • Lienor must record formal Claim of Lien within 90 days of last furnishing in county public records.
🏠 Home Hub

Florida Construction Lien Law (Fla. Stat. § 713.06) Knowledge Base

What is a 'Notice to Owner' (NTO) under Florida Statutes § 713.06?
Under Florida Statutes § 713.06(2)(a), all lienors not in direct privity with the owner (except professional lienors and laborers) must serve a written Notice to Owner on the owner, direct contractor, and lender as a condition precedent to perfecting a construction lien. The NTO informs the owner that the lienor is providing services or materials and that the owner must protect itself by ensuring the lienor is paid before disbursing funds to the direct contractor.
What is the strict 45-day deadline for serving an NTO under § 713.06(2)(a)?
Under Fla. Stat. § 713.06(2)(a), the Notice to Owner must be served before commencing, or not later than forty-five (45) calendar days after commencing, to furnish his or her labor, services, or materials, but in any event before the date of the direct contractor's final payment affidavit under § 713.06(3)(d)1. The 45-day window is strict and cannot be extended. If the 45th day falls on a weekend or legal holiday, Florida law allows service on the next business day.
What constitutes an 'Improper Payment' by a Florida property owner under § 713.06(3)?
An owner makes an 'improper payment' if the owner pays the direct contractor: (1) After receiving a timely Notice to Owner from a subcontractor without first obtaining a partial or final lien waiver from that subcontractor; (2) Without requiring the contractor to provide a statutory Final Contractor Payment Affidavit at the completion of the project; or (3) Prior to recording a valid Notice of Commencement under § 713.13. If an owner makes improper payments, the owner's property remains subject to liens up to the full contract price plus the amount improperly paid.
What is the 'Mailbox Rule' for serving an NTO under Florida Statutes § 713.18?
Under Florida Statutes § 713.18, service of a Notice to Owner by certified mail is legally effective as of the date of mailing, provided that: (1) The notice is mailed with certified mail tracking within forty (40) days after the date the lienor first furnished labor or materials; and (2) The lienor maintains official United States Postal Service electronic proof of delivery or tracking records. If mailed after day 40 but on or before day 45, service is only effective upon actual receipt by the owner.
What is the requirement and legal effect of the Final Contractor's Affidavit under § 713.06(3)(d)?
Under Florida Statutes § 713.06(3)(d)1, when the final payment under a direct contract becomes due, the contractor must give the owner an affidavit under oath stating either that all lienors have been paid in full or listing the names and amounts due to each unpaid lienor. The contractor has no lien or right of action against the owner until at least 5 days after delivering this affidavit. An owner who pays the direct contractor without receiving this affidavit makes an improper payment as a matter of law.