Florida Statutes § 713.06 Final Contractor Payment Affidavit Auditor

Statutory Compliance with Fla. Stat. § 713.06(3)(d), 5-Day Pre-Suit Condition Precedent & Lien Foreclosure Validity

1. Direct Contract & Litigation Timeline

2. Affidavit Content & Execution (§ 713.06(3)(d))

Statutory Condition Precedent Determination

CONDITION PRECEDENT SATISFIED
Final Contractor's Affidavit delivered at least 5 days prior to filing suit. Condition precedent fully met under Fla. Stat. § 713.06(3)(d)(1).
Actual Days Elapsed (Delivery to Lawsuit): 6 Days
Mandatory Minimum Statutory Gap: 5 Full Days (Fla. Stat. § 713.06(3)(d))
1-Year Lien Expiration Deadline (§ 713.22): February 1, 2027
Enforceable Lien Claim Sum: $145,000
Motion to Dismiss Exposure: IMMUNE (Precedent Met)

Florida Construction Lien Law Summary

Holding Electric Precedent: COMPLIANT (530 So. 2d 301)
Owner Proper Payment Defense: Triggered upon payment on affidavit
Subcontractor Affidavit Requirement: None (Direct Contractor Only)

Florida Statutes § 713.06(3)(d) Statutory Requirements & Precedents

Under Florida Statutes § 713.06(3)(d)(1), when final payment becomes due the contractor under a direct contract, the contractor must deliver a sworn affidavit stating either that all lienors have been paid in full or listing the names and amounts due to unpaid lienors.

The 5-Day Pre-Suit Jurisdictional Rule:

Subcontractor Distinction: Subcontractors, sub-subcontractors, and materialmen who do not have privity of contract with the owner are governed by the Notice to Owner rules (§ 713.06(2)) and are NOT required to furnish a final contractor payment affidavit.

Frequently Asked Questions (Florida Final Contractor Affidavit)

What is the contractor's final payment affidavit under Florida Statutes § 713.06(3)(d)?

Under Florida Statutes § 713.06(3)(d)(1), when final payment under a direct contract becomes due, the contractor must give the owner a sworn affidavit stating that all lienors under the direct contract have been paid in full, or listing the names of lienors who have not been paid and the amounts due or to become due to each.

What is the mandatory 5-day pre-suit condition precedent?

Under Florida Statutes § 713.06(3)(d)(1), the contractor must deliver the final affidavit to the owner at least five (5) days before instituting any lawsuit on the contract or to enforce a construction lien. Delivering the affidavit at least 5 days prior is a strict jurisdictional condition precedent to maintaining the lawsuit.

What happens if a contractor files a lien foreclosure lawsuit without the 5-day affidavit?

Under Florida Supreme Court precedent (Holding Electric, Inc. v. Roberts), failure to deliver the affidavit at least 5 days prior to filing suit bars the action. If the 1-year statute of limitations under § 713.22 expires before a proper affidavit and lawsuit are re-filed, the lien is permanently extinguished.

Do subcontractors have to furnish a final contractor payment affidavit?

No. The final payment affidavit requirement under § 713.06(3)(d) applies strictly to direct contractors having a direct contractual relationship with the owner. Subcontractors and sub-subcontractors are not required to furnish this affidavit.

How does the final affidavit protect the property owner?

Under Florida Statutes § 713.06(3)(c), if an owner makes final payment to the direct contractor in reliance on a proper contractor's final payment affidavit, the payment is deemed a 'proper payment', protecting the owner and property from liens of unlisted lienors who failed to timely serve a Notice to Owner.