Federal Miller Act Payment Bond Auditor

40 U.S.C. §§ 3131–3134 Statutory Claim Standing, 90-Day Notice & 1-Year Federal Lawsuit Deadlines

Contract & Claim Details

Statutory Bond Claim Audit

Claimant Standing
-
90-Day Notice Deadline
-
1-Year Lawsuit Deadline
-
Earliest Suit Filing Date
-
Statutory Requirement Miller Act Rule Claim Data Compliance Verdict

Frequently Asked Questions (Federal Miller Act)

Who has standing to make a payment bond claim under the Miller Act?
Under 40 U.S.C. § 3133(b), standing is restricted to two tiers: (1) First-tier claimants who contract directly with the prime contractor (first-tier subcontractors and materialmen), and (2) Second-tier claimants who contract with a first-tier subcontractor. Third-tier claimants (such as suppliers to a supplier or sub-subcontractors of a second-tier sub) lack statutory standing under MacEvoy Co. v. United States.
What is the 90-day notice rule under the Miller Act?
Second-tier claimants having no direct contractual relationship with the prime contractor must give written notice of their claim to the prime contractor within 90 days from the date on which they performed the last labor or furnished the last material for which the claim is made (40 U.S.C. § 3133(b)(2)). First-tier claimants are not required to give this 90-day notice.
What is the statute of limitations for filing a Miller Act lawsuit?
A Miller Act lawsuit must be brought in the United States District Court for any district in which the contract was to be performed within one year after the day on which the last labor was performed or material supplied by the claimant (40 U.S.C. § 3133(b)(4)). In addition, the suit cannot be commenced before the expiration of 90 days after the last work.