Audit District of Columbia mechanics lien statutory compliance under D.C. Code § 40-301.01 et seq.: 90-day Notice of Intent to claim a lien recording deadline in Recorder of Deeds, 5-day certified mail service on owner, and 180-day lawsuit filing with lis pendens in D.C. Superior Court (§ 40-303.13).


Frequently Asked Statutory Questions

Under D.C. Code § 40-301.02, a contractor, subcontractor, or material supplier must record a Notice of Intent to Hold and Claim a Lien in the office of the D.C. Recorder of Deeds within ninety (90) days after the earlier of the completion or termination of the project.

Under D.C. Code § 40-301.02(b), within five (5) business days after the Notice of Intent is recorded, the claimant must serve a copy of the notice on the property owner by certified mail. If the certified mail is returned unclaimed, posting on the property is required within five days.

Under D.C. Code § 40-303.13, an action to enforce the lien must be commenced in the Superior Court of the District of Columbia and a notice of pendency of action (lis pendens) must be recorded in the Recorder of Deeds within one hundred eighty (180) days after the Notice of Intent was recorded. Missing this 180-day deadline voids the lien automatically.