Colorado Mechanics Lien Notice of Intent Auditor | C.R.S. § 38-22-109

Audit statutory deadlines under Colorado Revised Statutes § 38-22-109: mandatory 10-day Notice of Intent to File Lien Statement, 4-month recording, and 6-month foreclosure lawsuit limit.

🏠 Home Hub

Statutory & Regulatory FAQs

What is the mandatory 10-day Notice of Intent under C.R.S. § 38-22-109(3)?
Under Colorado Revised Statutes § 38-22-109(3), at least 10 calendar days before recording a lien statement with the county clerk and recorder, the claimant MUST serve a Notice of Intent to File a Lien Statement, together with a copy of the proposed lien statement, upon the property owner or their reputed agent and the principal contractor by personal service or registered/certified mail. Recording without this 10-day advance notice completely invalidates the lien.
What are the recording deadlines for mechanics lien statements in Colorado?
Under C.R.S. § 38-22-109(4) & (5): (1) For labor and work by the day or piece without furnishing materials, the lien statement must be filed within 2 months after completion of the building; (2) In all other cases (contractors, subcontractors, materialmen), the lien statement must be filed within 4 months after the day on which the last labor was performed or last materials furnished.
What is the statute of limitations to foreclose a Colorado mechanics lien?
Under C.R.S. § 38-22-110, an action to enforce the lien must be commenced in the district court within 6 calendar months after the date of the last work performed, materials furnished, or the completion of the building. In addition, a notice of lis pendens must be recorded in the county land records within the same 6-month window.