Colorado Mechanics' Lien 10-Day Notice of Intent & Deadline Auditor

C.R.S. Title 38, Article 22 Compliance, 10-Day Service Rules, 4-Month Recording & 6-Month Foreclosure Limits

Project Work & Notice Timelines

Colorado Statutory Audit Findings

Lien Timelines Compliant
Notice of Intent Waiting Period: 15 Calendar Days (>= 10 Days)
4-Month Recording Deadline (§ 38-22-109(5)): 2026-12-01
6-Month Foreclosure Deadline (§ 38-22-110): 2027-02-01
Notice of Intent Validity: Satisfied (>= 10 Days Pre-Recording)
Excessive Lien Forfeiture Risk (§ 38-22-201): $0 (Bona Fide Debt)

Statutory Procedure Synthesis

The 10-day Notice of Intent was served with 15 days clearance prior to recording. Lien statement will be recorded within the mandatory 4-month statutory window under C.R.S. § 38-22-109(5).

Mandatory Colorado Lien Rules:

  • Service on Both Parties: Service must be made on BOTH the property owner and the principal contractor.
  • Exact Copy Required: Failure to attach the proposed lien statement to the Notice of Intent invalidates the lien.
  • Lis Pendens Mandatory: Foreclosure action is ineffective unless a notice of lis pendens is recorded with the county within the 6-month window.
🏠 Home Hub

Colorado Mechanics' Lien Statutory Guidance

What is the mandatory 10-Day Notice of Intent to File Lien under C.R.S. § 38-22-109(3)?
Under Colorado Revised Statutes § 38-22-109(3), at least 10 days before recording a lien statement with the county clerk and recorder, the claimant MUST serve a Notice of Intent to File a Lien Statement, together with a complete copy of the lien statement, personally or by registered or certified mail return receipt requested, upon the property owner (or owner's agent) and the principal contractor. An affidavit of service or the certified mail return receipt must be recorded along with the lien statement.
What is the recording deadline for a Colorado mechanics' lien statement?
Under C.R.S. § 38-22-109(5), a lien statement for all claimants (other than day-laborers) must be recorded within four calendar months after the day on which the last work was performed or the last materials or equipment were furnished. For laborers paid by the day or piece, the deadline is two months. Notice of Intent must be served at least 10 days before this 4-month deadline expires.
What is the foreclosure enforcement deadline under C.R.S. § 38-22-110?
Under C.R.S. § 38-22-110, an action to enforce and foreclose a mechanics' lien must be commenced in district court within six calendar months after the last work was performed or materials furnished. A notice of lis pendens must be recorded in the county real property records concurrently with the lawsuit. Failure to file within six months extinguishes the lien entirely.
What are the penalties for filing an excessive or frivolous lien in Colorado?
Under C.R.S. § 38-22-201, any person who files a lien statement for an amount greater than is due without a reasonable possibility that the amount claimed is due, or with knowledge that the amount is greater than that for which the property is liable, shall forfeit all rights to the lien and shall be liable to the person aggrieved for all costs and reasonable attorney fees.