What are the prompt payment deadlines in California private construction?
Under Cal. Civ. Code § 8800, a property owner must pay progress payments to direct contractors within 30 days of receiving an undisputed pay application. Under Civil Code § 8814, direct contractors must pay their subcontractors within 7 calendar days after receiving progress funds from the owner.
How does the 150% dispute withholding rule work?
Under Civil Code § 8800(b) and § 8814(b), if there is a genuine good-faith dispute over work quality or punchlist items, the paying party may withhold up to 150% of the disputed amount. Any amount withheld in excess of 150% of the legitimate dispute is immediately subject to the 2% monthly statutory penalty.
Can the 2% monthly penalty be waived by contract?
No. Under Cal. Civ. Code § 8800(d) and § 8814(d), any contract provision waiving or modifying prompt payment rights and penalties is against public policy, null, and void. In litigation, the prevailing party is statutorily entitled to recover reasonable attorney's fees.