Statutory Recording Window under Cal. Civ. Code §§ 8412 & 8414, Notice of Completion Validity (§ 8182) & 90-Day Foreclosure Limit (§ 8460)
In California private construction projects, the deadlines for recording a claim of mechanic's lien are strict jurisdictional requirements governed by California Civil Code §§ 8412 and 8414:
Under California Civil Code § 8412, a direct contractor must record a claim of lien after complete performance of the contract, and before the earlier of: (1) 90 days after completion of the work of improvement; or (2) 60 days after the owner records a valid Notice of Completion or Notice of Cessation.
Under California Civil Code § 8414, a claimant other than a direct contractor must record a claim of lien before the earlier of: (1) 90 days after completion of the work of improvement; or (2) 30 days after the owner records a valid Notice of Completion or Notice of Cessation.
Under California Civil Code § 8182, an owner must record the Notice of Completion within fifteen (15) days after the actual date of completion. If recorded prematurely (before completion) or late (more than 15 days after completion), the Notice of Completion is legally ineffective, restoring the default 90-day recording window for all claimants.
Under California Civil Code § 8460, the claimant must commence an action to enforce (foreclose) the lien within ninety (90) days after the claim of lien is recorded. If suit is not filed within 90 days, the lien automatically expires and becomes unenforceable unless an extension of credit is recorded under § 8460(b).
Completion of a work of improvement occurs upon: (1) actual completion of the work; (2) occupation or use by the owner accompanied by cessation of labor; (3) cessation of labor for a continuous period of 60 days; or (4) recordation of a notice of cessation after continuous cessation of labor for 30 days.