What is the 20-day preliminary notice requirement in Arizona?
Under A.R.S. § 33-992.01, every claimant (except an original contractor having a direct contract with the owner or a person performing actual labor for wages) must give a written 20-day preliminary notice to the owner, general contractor, and construction lender within 20 days of first furnishing labor or materials. A late notice only preserves lien rights for labor/materials furnished within the 20 days preceding service and thereafter.
What are the recording deadlines for mechanics' liens in Arizona?
Under A.R.S. § 33-993, the standard deadline to record a Notice and Claim of Lien with the County Recorder is 120 days after completion of the improvement. However, if the owner records and serves a valid Notice of Completion, the recording deadline is shortened to 60 days after recording of that notice.
How long is an Arizona mechanics' lien valid before a lawsuit must be filed?
Under A.R.S. § 33-998, a mechanics' lien remains valid for only six months after recording with the County Recorder. A foreclosure action must be filed in Superior Court and a Lis Pendens recorded within that strict 6-month period, otherwise the lien automatically expires and becomes void.