Arizona Mechanics Lien 20-Day Preliminary Notice & Recording Auditor | A.R.S. § 33-981
Audit Arizona mechanics lien requirements under A.R.S. § 33-992.01 20-day Preliminary Notice, 120-day / 60-day Notice of Completion recording (A.R.S. § 33-993), and 6-month lawsuits.
Statutory Provisions & Frequently Asked Questions
What is the 20-Day Preliminary Notice rule under Arizona A.R.S. § 33-992.01?
Under A.R.S. § 33-992.01, every claimant (general contractors, subcontractors, suppliers, and equipment lessors) must serve a written 20-Day Preliminary Twenty-Day Notice on the property owner, original contractor, and construction lender within 20 days of first furnishing labor or materials. If served late, the notice only covers work furnished up to 20 days prior to the date of service.
Can subcontractors lien an owner-occupied residence in Arizona?
No. Under A.R.S. § 33-981(C), only a person who has a direct written contract with the owner-occupant of a dwelling can enforce a mechanics lien against that owner-occupied residential property. Subcontractors and material suppliers lacking direct contractual privity with the homeowner are legally barred from placing a lien on an owner-occupied residence.
What is the deadline for filing a lien foreclosure action in Arizona?
Under A.R.S. § 33-998, an action to foreclose a mechanics lien must be commenced in the superior court of the county where the property is located within 6 calendar months from the date the Notice and Claim of Lien was recorded. If no action is filed within 6 months, the lien expires and is legally void.