Construction & Mechanics Lien Law

Alaska Mechanics' Lien Statutory Compliance Auditor | AS § 34.35.050

Audit Alaska mechanics lien compliance under Alaska Statutes Title 34, Chapter 35 (AS §§ 34.35.050 - 34.35.120): Notice of Right to Lien (§ 34.35.064), 120-day vs 15-day Notice of Completion deadlines (§ 34.35.071), and 6-month foreclosure lawsuit statutes.


Frequently Asked Statutory Questions

Under AS § 34.35.064, a potential lien claimant (other than an individual laborer) may record and serve a Notice of Right to Lien on the owner. Doing so preserves the claimant's lien rights against subsequent purchasers and encumbrancers, preventing the owner from asserting the defense of payment to the general contractor.

Under AS § 34.35.071, if the property owner records and serves a valid statutory Notice of Completion, the lien recording deadline for all claimants is dramatically truncated from the standard 120 days down to just fifteen (15) days from the date the Notice of Completion is recorded.

Under AS § 34.35.110, an action to enforce a mechanics lien in Alaska must be commenced in the Alaska Superior Court within six (6) months after the claim of lien is recorded. If no action is filed within 6 months, the lien expires and is unenforceable as a matter of law.