Alabama Mechanics Lien Statutory Guidance
What is the difference between a 'full price lien' and an 'unpaid balance lien' in Alabama?
Under Alabama Code § 35-11-218, a subcontractor or material supplier who gives written notice to the property owner BEFORE furnishing materials or labor obtains a 'full price lien' securing the full agreed contract price, unless the owner notifies them in writing that the owner will not be responsible. If no prior notice is given before delivery, the claimant only obtains an 'unpaid balance lien', which is strictly capped at whatever remaining funds the owner owes to the original general contractor at the time statutory notice of lien intent is delivered.
What are the statutory recording deadlines in the Alabama Probate Court?
Under Ala. Code § 35-11-215, a verified statement of lien must be recorded in the Office of the Judge of Probate in the county where the property is located: (1) within 30 days after the last work performed for day laborers and journeymen; (2) within 6 months after the entire indebtedness accrues for original contractors (general contractors with direct owner privity); and (3) within 4 months after the indebtedness accrues for all other claimants, including subcontractors and material suppliers.
What is the statute of limitations to enforce an Alabama mechanics lien?
Under Ala. Code § 35-11-221, an action to enforce an Alabama mechanics lien must be commenced in the Circuit Court of the county where the real property is situated within six (6) months after the maturity of the entire indebtedness. Failure to file a complaint in Circuit Court within this 6-month period renders the mechanics lien completely void and unenforceable.