Model EPA and state environmental agency Construction General Permit (CGP) compliance under Clean Water Act Section 402 (33 U.S.C. § 1342) and 40 CFR § 122.26: evaluate 1.0-acre soil disturbance threshold for NPDES stormwater permitting, mandatory Stormwater Pollution Prevention Plan (SWPPP) elements, Qualified Inspector certifications, routine site inspection frequencies (weekly vs bi-weekly + 24-hr post-0.25 inch rain), sediment basin sizing (3,600 cubic feet per acre drained), and final site stabilization standards (70% vegetative cover).
| NPDES CGP Requirement | EPA 2022 CGP Standard | Audit Result |
|---|---|---|
| NPDES Permit Applicability | Mandatory for ≥ 1.0 Acre Disturbance | Pending |
| Notice of Intent (NOI) Filing | File 14 Days Prior to Earthwork | Pending |
| Inspection Schedule Validity | 7-Day or 14-Day + Rain Trigger | Pending |
| Sediment Basin Storage Sizing | 3,600 cu. ft. / Acre Drained | 0 cu. ft. |
| Stabilization Deadline | 14 Days (Standard) / 7 Days (Impaired) | Pending |