Audit industrial emissions to determine whether your facility triggers mandatory Title V Major Source operating permit requirements. Calculate Potential to Emit (PTE), nonattainment area threshold multipliers, and Synthetic Minor federally enforceable permit caps.
EPA calculates Title V status based on maximum capacity operating 8,760 hours/year (24/7/365). Even if a plant operates only one 40-hour shift per week, its uncontrolled theoretical capacity determines Major Source status!
Facilities can legally avoid Title V by obtaining a "Synthetic Minor" state operating permit containing federally enforceable operational restrictions (e.g., fuel usage meters, solvent throughput caps) that hold actual PTE below 100 TPY.
Title V permits require a designated corporate officer (the "Responsible Official") to certify compliance under penalty of perjury annually. False statements or unpermitted exceedances carry individual criminal liability under 42 U.S.C. § 7413(c).