Under 40 CFR Part 68, the RMP rule requires facilities that hold more than a threshold quantity of a listed regulated toxic or flammable substance in a single process to develop a hazard assessment, prevention program, and emergency response plan.
Program 1 applies to processes with no offsite accident history and whose worst-case release does not reach public receptors. Program 3 applies to processes subject to OSHA PSM or specific high-hazard manufacturing sectors. Program 2 covers all other regulated processes.
Under 40 CFR § 68.190, the owner or operator must review and update the RMP at least once every 5 years, or within 6 months of a significant process change or change in chemical threshold.