Asbestos NESHAP (40 CFR Part 61) Demolition Auditor

Under 40 CFR Part 61, Subpart M (Clean Air Act § 112), owners and operators must notify the EPA or delegated state air authority at least 10 working days before commencing demolition or renovation activities involving Regulated Asbestos-Containing Material (RACM) above statutory threshold quantities.

Statutory RACM threshold: 260 linear feet
Statutory RACM threshold: 160 square feet
Statutory RACM threshold: 35 cubic feet
Mandatory 10-Working-Day Prior Notification Calendar
Click audit to generate calendar...
Regulatory Obligations
NESHAP Prior Written Notification Requirement
MANDATORY
Must notify EPA / State air authority 10 working days prior
Latest Date to Submit NESHAP Notice
--
Calculated based on 10 working days prior to start
Emission Control & Wetting Standards
ZERO VISIBLE EMISSIONS
Adequate wetting and leak-tight containerization mandatory
Civil & Criminal Penalties
  • Demolition Notice Rule: For demolitions, notification is mandatory even if zero asbestos is present (§ 61.145(a)(1)).
  • Federal Civil Fines: Up to $64,618 per day per violation under Clean Air Act Section 113.
  • Criminal Exposure: Knowing violations carry criminal penalties up to 5 years imprisonment.