Calculate construction contract retainage withholdings, statutory retainage limits (California 5% public cap, Texas 10% statutory retainage, New York 5% private cap), release timelines, and mandatory escrow interest penalties across all 50 states.
Frequently Asked Questions
What is Texas statutory retainage under Property Code Chapter 53?
In Texas, real estate property owners are legally required by statute (Tex. Prop. Code § 53.025) to withhold exactly 10% of the contract price from the general contractor until 30 days after the project is completed. This statutory retainage fund exists specifically to secure payment for subcontractors and material suppliers.
Can a California public agency withhold 10% retainage?
No! Under California Public Contract Code § 7201, public agencies (cities, school districts, state agencies) cannot withhold more than 5% retainage from progress payments, unless the governing board formally approved a higher rate in the bid specifications due to extreme project complexity.
What is the penalty for withholding retainage past the deadline in California?
Under California Public Contract Code § 7107, if retainage is improperly withheld past 60 days after project completion, the contractor is legally entitled to a mandatory statutory penalty of 2% per month on the improperly withheld funds, plus attorney fees.