US Construction Pay-If-Paid vs Pay-When-Paid Contingent Clause Analyzer

Analyze construction contingent payment clauses (Pay-if-Paid vs Pay-when-Paid) against state public policy prohibitions (CA, NY, NC, MA, IL) and express condition precedent requirements.

Frequently Asked Questions

A 'Pay-when-Paid' clause is merely a timing mechanism requiring the general contractor to pay the subcontractor within a reasonable time after invoicing, regardless of whether the owner ever pays the GC. A 'Pay-if-Paid' clause attempts to make owner payment an express condition precedent, shifting the entire financial risk of the owner's insolvency or bankruptcy onto the subcontractor.

In leading jurisdictions like California (Wm. R. Clarke Corp. v. Safeco) and New York (West-Fair Elec. v. Aetna), courts struck down pay-if-paid clauses specifically because they indirectly waived or extinguished mechanic's lien rights in violation of state public policy.

No. Under the universal legal 'prevention doctrine', a party cannot insist on the performance of a condition precedent when that party itself caused the non-performance. If the owner withheld payment because of the general contractor's defective work or delays, the GC cannot hide behind a pay-if-paid clause to refuse payment to innocent subcontractors.
Legal & Statutory Context

This statutory tool references standard legal authorities including state commercial codes, civil and property statutes, Uniform Acts (UCC, UPOAA, UTC, URPTODA), prompt payment acts, and OSHA / Federal standards.

Updated to reflect current statutory amendments and compliance requirements for all 50 US jurisdictions.