Under Utah Code § 38-1a-501, any person who desires to claim a construction lien must file a preliminary notice with the State Construction Registry (SCR) within 20 days after commencing work. If filed later than 20 days, the lien covers only work performed beginning 5 days after the notice is filed.
Under Utah Code § 38-1a-502, a claimant must record a written notice of construction lien in the county recorder's office within 180 days after the day on which final completion occurs, OR within 90 days after a Notice of Completion is filed on the SCR.
Under Utah Code Title 38 Chapter 9 (Wrongful Liens), recording a known groundless or invalid lien exposes the claimant to statutory damages of $10,000 or treble actual damages (whichever is greater), plus mandatory attorney fees and costs.