Evaluate statutory compliance under Texas Property Code § 53.101. Property owners must retain 10% of the contract price (or value of work) for 30 days after project completion to secure derivative claimant liens.
Under Texas law: (1) During the progress of work and for 30 days after the work is completed, the owner must retain 10% of the contract price or 10% of the value of work, (2) The statutory retainage fund secures the payment of artisans, mechanics, subcontractors, and material suppliers who send timely pre-lien notice, (3) Under § 53.105, if the owner fails to retain the statutory 10%, claimants who comply with Chapter 53 have a direct lien on the owner's property and the owner is personally liable to the extent of the retainage that should have been withheld.