Texas Ch. 53 Retainage & Specially Fabricated Materials Auditor

Under Tex. Prop. Code § 53.101 et seq., owners are statutorily required to retain 10% of the contract price or value of work during progress and for 30 days post completion. Subcontractors for specially fabricated materials enjoy unique early notice rights even if materials are never delivered.

Texas Statutory Notice & Filing Timeline Matrix
Click calculate to generate statutory calendar...
Retainage Fund Liability
Total Adjusted Contract Value
$895,000
Mandatory 10% Retainage Fund (§ 53.101)
$89,500
Owner Retainage Shortfall / Liability Exposure
$24,500
Owner Personally Liable for Difference
Texas Prop. Code § 53.105 Key Rules
  • 30-Day Retainage Window: Claimants must send notice of retainage claim within 30 days after work completion or contract termination.
  • Owner Exposure: Failure to retain 10% makes owner personally liable to valid lien claimants to the extent of 10% fund.
  • Specially Fabricated Materials (§ 53.058): Notice must be sent to owner by the 15th day of the 2nd month after receiving order, protecting claim even if materials are uninstalled.
Retainage Fund Summary
Required Statutory 10%:$89,500
Actually Retained:$65,000
Owner Deficit:$24,500
Fabrication Protection:$38,000