During the progress of work and for 30 days after work is completed, an owner must retain either 10 percent of the contract price or 10 percent of the value of the work completed. This statutory retainage fund exists to protect subcontractors and materialmen who have valid lien claims.
Under Texas 2022 revised lien laws, second-tier subcontractors must send fund trapping notice by the 15th day of the third month following each month labor/materials were provided. Commercial lien affidavits must be filed with the county clerk by the 15th day of the fourth month after the indebtedness accrued, or 30 days after contract completion for retainage.