Tennessee Lien Law

Tennessee Mechanics Lien & Notice to Owner Auditor (T.C.A. § 66-11)

Calculate Tennessee 90-day Notice of Nonpayment deadlines under T.C.A. § 66-11-145, evaluate prime contractor Notice of Lien recording requirements, and audit commercial foreclosure periods.

Statutory Guidance & FAQs

Under T.C.A. § 66-11-145, remote contractors (subcontractors and suppliers) on commercial projects must serve a formal Notice of Nonpayment on the property owner and prime contractor within 90 days after the end of each month in which work or materials were furnished and remained unpaid. Failure to serve this notice defeats lien rights for that month's work.

Prime contractors in direct privity have 1 year from project completion to record a Notice of Lien. Remote contractors must record their Notice of Lien within 90 days after the prime contractor's work is completed or abandoned, OR within 10 days if the owner records a Notice of Completion under T.C.A. § 66-11-143.