Model the common law "Joint Check Rule" presumption under Post Bros. Construction v. Yoder, avoid unintentional mechanics lien releases, and draft protective tripartite joint check agreements.
Under California law (Post Bros. Constr. Co. v. Yoder, 20 Cal.3d 1), when a general contractor issues a joint check to a subcontractor and supplier, the supplier is conclusively presumed to have received payment up to the full face value of the check for materials furnished on that project.
If a supplier endorses a $65,000 joint check and hands it back to the subcontractor, trusting the subcontractor to pay them later, the supplier's mechanics lien and bond rights are deemed 100% SATISFIED AND DISCHARGED under the Joint Check Rule, even if the sub never pays them a penny!
A formal written Joint Check Agreement prevents misunderstanding by requiring the supplier to deposit the joint check directly, withhold its exact invoiced sum, and remit the remaining labor balance to the subcontractor.