South Carolina Mechanics Lien & Notice of Furnishing Auditor

Audit compliance deadlines for South Carolina Notice of Furnishing under S.C. Code § 29-5-20, calculate 90-day Notice of Lien recording deadlines, and track 6-month lawsuit statutes of limitations.

Statutory Guidance & FAQs

Under S.C. Code Ann. § 29-5-20(B), a remote subcontractor or supplier must deliver a Notice of Furnishing to the project owner and general contractor. This statutory notice limits the owner's defense that payments were already made to the general contractor and locks in the owner's direct liability to the extent of remaining contract funds.

Under S.C. Code Ann. § 29-5-90, a Notice and Certificate of Lien must be filed with the register of deeds or clerk of court within 90 days after the claimant ceases to furnish labor or materials. Under § 29-5-120, a lawsuit to enforce and foreclose the lien must be commenced within 6 months after the claimant ceases labor.