South Carolina Title 29 Mechanics' Lien Auditor

Under S.C. Code Ann. § 29-5-10 et seq., a mechanic or materialman must record a Notice of Lien in the county Register of Deeds within 90 days of ceasing to furnish labor or materials, and file a lawsuit to enforce the lien within 6 months of ceasing work.

South Carolina Statutory Calendar Matrix
Click audit to generate calendar...
South Carolina Lien Status
Record Notice of Lien Deadline (§ 29-5-90)
--
Strict 90 calendar days from last furnishing
Foreclosure Lawsuit Filing Deadline (§ 29-5-120)
--
Strict 6 calendar months from last furnishing
Subcontractor Defense of Payment Exposure
PROTECTED
Notice of furnishing served before owner paid prime
South Carolina Statutory Rules
  • Defense of Payment (§ 29-5-40): Owner's total lien liability to subcontractors cannot exceed the amount unpaid to prime contractor at the time notice is received.
  • Lis Pendens Mandate: Claimant must file a Lis Pendens concurrently with the foreclosure complaint within the 6-month statutory window.