Rhode Island Mechanics' Lien R.I. Gen. Laws § 34-28-4 Auditor

Audit Rhode Island mechanics lien procedures: 200-day notice of intention to claim lien, certified mail to owner, and 40-day petition in equity foreclosure (§ 34-28-10).
Rhode Island General Laws (R.I. Gen. Laws) Title 34 Chapter 28 (Mechanics' Liens)

Statutory Parameters

Statutory Compliance FAQ (People Also Ask)

What is the deadline to record a Notice of Intention in Rhode Island?

Under R.I. Gen. Laws § 34-28-4, a claimant must file a Notice of Intention to Claim a Lien in the land evidence records of the city or town within two hundred (200) days of doing work. The lien is effective only for work performed or materials furnished during the 200-day window immediately preceding the filing.

What is Rhode Island's 40-day petition in equity requirement?

Under R.I. Gen. Laws § 34-28-10, after recording the Notice of Intention, the claimant must file a complaint and petition in equity in the Superior Court to enforce the lien within forty (40) calendar days of filing the notice, or the lien is permanently void.

Must a notice of lis pendens be recorded in Rhode Island?

Yes. Under R.I. Gen. Laws § 34-28-10, at the exact time of filing the complaint in Superior Court, the claimant must also record a notice of lis pendens in the city or town land evidence records.