Oklahoma Title 42 Mechanics' & Materialmen's Lien Pre-Lien Notice Auditor

Calculate statutory pre-lien notice windows (within 75 days of last work date for non-owner occupied property), 4-month county clerk lien filing for general contractors vs 90 days for subcontractors, and 1-year lawsuit enforcement deadlines under 42 O.S. § 141 et seq.


Oklahoma Title 42 Project Details

Pre-lien required for claims > $10,000 on commercial.
Oklahoma Mechanics' Lien Statutes (42 O.S. § 141)
  • Pre-Lien Notice (§ 142.6): For claims exceeding $10,000 on commercial property or multi-family residential, subcontractors must serve a written pre-lien notice on the owner and general contractor no later than 75 days after last furnishing.
  • Lien Filing Deadlines (§ 142 & § 143): Original general contractors have four (4) months from the date of last furnishing to file a lien statement with the County Clerk. Subcontractors and materialmen have ninety (90) days.
  • One-Year Lawsuit Window (§ 172): A lawsuit to foreclose the mechanics' lien must be commenced in district court within one (1) year from the filing date of the lien statement.

Oklahoma Statutory Timeline

Click "Audit Oklahoma Mechanics' Lien Deadlines" to calculate exact pre-lien notice cutoffs, county clerk filing dates, and foreclosure windows.