Under NMSA 1978 § 48-2-2.1, any subcontractor, material supplier, or equipment lessor who does not contract directly with the owner on a commercial project exceeding $5,000 must serve a written preliminary notice on the owner within 60 days of first furnishing labor or materials.
Under NMSA 1978 § 48-2-6, an original/prime contractor must record a claim of lien with the county clerk within 120 days after completion of the contract. Subcontractors and suppliers must record within 90 days after completion of the building or improvement.
Under NMSA 1978 § 48-2-10, an action to enforce a mechanics lien must be commenced in district court within two (2) years after the claim of lien is recorded; otherwise, the lien expires and becomes void.