Audit Missouri mechanics lien requirements under Mo. Rev. Stat. § 429: mandatory GC disclosure notices, subcontractor 10-day Notice of Intent to File Lien, 6-month recording deadlines, and 6-month foreclosure suits.
Statutory Guidance & FAQs
Under Mo. Rev. Stat. § 429.012, every original contractor must provide the property owner with a statutory disclosure notice in at least 10-point bold type prior to receiving any payment, stating that subcontractors and suppliers may place liens if unpaid. Providing this notice is a strict condition precedent to the creation of any lien by the original contractor.
Under Mo. Rev. Stat. § 429.100, every person other than an original contractor must give 10 days' written notice to the owner prior to filing a mechanics lien. The lien itself must be filed in the circuit court clerk's office within 6 months after the indebtedness accrued (final furnishing date).