Michigan Construction Lien Act Notice of Furnishing & Foreclosure Auditor

Audit mechanic's lien deadlines under Michigan Compiled Laws (MCL) § 570.1101, tracking the 20-day Notice of Furnishing (MCL 570.1109), 90-day Claim of Lien recording (MCL 570.1111), and 1-year foreclosure suit statutory windows.

Construction & Real Estate Law US Statutory Standard
Michigan Project Timelines MCL § 570.1101 et seq.
Statutory Lien Audit
Enter project dates to audit Michigan lien perfection timeline.
Michigan Statutory Mechanics
  • Notice of Furnishing (MCL 570.1109): Must be served within 20 days of first furnishing. Direct contractors are exempt. Late notice limits lien to payments made after notice receipt.
  • Claim of Lien (MCL 570.1111): Must be recorded with the County Register of Deeds within 90 days after last furnishing labor/materials.
  • Foreclosure (MCL 570.1117): Must file civil foreclosure action in circuit court within 1 year from recording date.