Maryland Mechanics' Lien Real Prop. § 9-104 & § 9-105 Auditor

Audit Maryland mechanics lien judicial procedures: 120-day Notice of Intention to Claim a Lien to owner (§ 9-104), 180-day Petition to Establish Mechanics' Lien in Circuit Court (§ 9-105), show cause order, and interlocutory lien hearings.

Maryland Code Annotated, Real Property Article Title 9 (§ 9-101 - § 9-114)

Auditor & Modeler Input Parameters

Statutory Audit & Analysis Results

Click "Run Compliance Audit & Model" to generate report.

Statutory Legal Citations & Frequently Asked Questions

How does Maryland's mechanics' lien process differ from other states?
In Maryland, a contractor or subcontractor does not have an automatic lien upon recording a document in land records. Instead, under Real Property § 9-105, the claimant must file a petition in Circuit Court, after which the court conducts a show cause hearing to determine whether to enter an order establishing the lien.
What is the 120-day notice requirement for Maryland subcontractors?
Under Md. Real Prop. § 9-104, a subcontractor who has not contracted directly with the property owner must serve written notice of intention to claim a lien upon the owner within 120 days after doing work or furnishing materials.
What is the 15% building valuation rule under Maryland Real Property § 9-102?
Under § 9-102(a), every building erected and every building repaired, rebuilt, or improved to the extent of 15 percent of its value is subject to a lien. If a repair project does not equal at least 15% of the building's value, it is not eligible for a mechanics' lien.