Louisiana Private Works Act (La. R.S. 9:4801) Statement of Claim & Privilege Auditor

Calculate Louisiana Private Works Act Statement of Claim and Privilege recording deadlines (60 days from Notice of Termination of Work, or 60 days from substantial completion if no notice), 1-year lawsuit lis pendens window, and equipment lessor notices under La. R.S. 9:4801 et seq.


Louisiana Private Works Act Project Parameters

Louisiana Private Works Act Rules (La. R.S. 9:4801 et seq.)
  • 60-Day Privilege Rule: If a Notice of Contract is filed, subcontractors, materialmen, and laborers must record their Statement of Claim and Privilege within sixty (60) days after the filing of a Notice of Termination of Work.
  • No Notice of Contract: If no Notice of Contract was filed, claimants have sixty (60) days after substantial completion or abandonment of the work.
  • One-Year Extinguishment & Lis Pendens: Under La. R.S. 9:4823, a claim and privilege is extinguished unless a lawsuit to enforce it is filed, AND a formal Notice of Lis Pendens is recorded in the mortgage records, within one (1) year from filing the Statement of Claim.

Louisiana Privilege Schedule

Click "Audit Louisiana Statement of Claim Deadlines" to calculate exact mortgage recordation cutoffs and lis pendens requirements.