Indiana Code IC 32-28-3 Mechanics' Lien & Sworn Statement Auditor

Calculate Indiana mechanics' lien recording deadlines (60 days for residential vs 90 days for commercial/industrial), 1-year foreclosure lawsuit windows, and pre-lien notice requirements under IC 32-28-3.


Indiana Mechanics' Lien Parameters

Indiana Code IC 32-28-3 Statutory Mandates
  • Residential 60-Day Rule: For Class 2 residential structures, the Sworn Statement and Notice of Intention to Hold a Lien must be recorded in the county recorder's office within 60 days of last furnishing.
  • Commercial 90-Day Rule: For commercial or other non-residential real estate, the lien must be recorded within 90 days of last furnishing.
  • Foreclosure Lawsuit: Must be filed within one (1) year of recording the lien, UNLESS the owner serves a formal notice demanding suit, in which case suit must be filed within 30 days.

Indiana Statutory Timeline Schedule

Click "Audit Indiana Mechanics' Lien Deadlines" to calculate exact recording deadlines and statutory pre-lien notice requirements.