Model Illinois Mechanics Lien Act statutory deadlines: 90-day subcontractor notice of claim to property owner and lending institution under 770 ILCS 60/24, 4-month recording deadline against third parties/purchasers under § 7, and 2-year lawsuit enforcement statute of limitations under § 9.
Base Value / Claim Amount
$0
Protected / Accrued Metric
$0
Exposure / Liability Total
$0
Statutory Notice Deadline
-
Legal / Compliance Status
-
Statutory Compliance FAQ & Legal Authorities
What is the mandatory 90-day subcontractor notice under 770 ILCS 60/24?
Under Section 24 of the Illinois Mechanics Lien Act (770 ILCS 60/24), subcontractors and suppliers who do not deal directly with the property owner must serve written notice of their claim on the owner (or owner's agent/architect) and the lending mortgage institution within 90 days after the completion of their labor or final delivery of materials. Service must be made via certified mail return receipt requested or personal delivery.
What special notice rules apply to owner-occupied single-family residences in Illinois?
Under 770 ILCS 60/5 and 60/24, for an existing owner-occupied single-family residence, a subcontractor must serve an initial notice to the owner within 60 days after first furnishing materials or labor, warning that a lien may be claimed. Failure to serve this 60-day preliminary notice preserves a lien only to the extent the owner has not already paid the general contractor.
What are the 4-month recording and 2-year lawsuit deadlines in Illinois?
Under 770 ILCS 60/7, a claimant must record the claim for lien in the county recorder's office within 4 months after final completion of work to enforce the lien against third-party purchasers, lenders, or encumbrancers. Under Section 9, a lawsuit to foreclose the lien must strictly be filed within 2 years after the date of final completion.
Embed This Auditor
Copy the code below to embed this tool into your website or client portal: