Calculate Georgia construction lien milestones: mandatory 30-day Notice to Contractor following Notice of Commencement under O.C.G.A. § 44-14-361.5, 90-day recording window from last work under § 44-14-361.1, and 365-day foreclosure lawsuit limit (or 60-day Notice to Contest Lien).

Statutory Compliance Findings

Statutory Primary Cutoff
--
Financial / Secondary Audit
--
Statutory Exposure / Cap
--
Compliance Status
Ready

Statutory Framework & Compliance Guide

This legal-grade auditing calculator analyzes critical statutory milestones, deadlines, and strict procedural requirements established by state and federal codes. Adherence to exact calendar calculation prevents catastrophic forfeiture of rights, civil penalties, or invalidation of legal instruments.

Frequently Asked Questions

What is Georgia's 30-day Notice to Contractor requirement under O.C.G.A. § 44-14-361.5?

Under Georgia law, if the owner or general contractor records a Notice of Commencement within 15 days of starting work, any subcontractor or supplier who does not have a direct contract with the general contractor must serve a written Notice to Contractor within 30 days from the filing of the Notice of Commencement OR 30 days from first furnishing labor or materials, whichever is later. Failure to serve this notice extinguishes all mechanics lien rights.

What is the deadline to record a Claim of Lien in Georgia?

Under O.C.G.A. § 44-14-361.1(a)(2), a Claim of Lien must be filed for recording in the office of the clerk of the superior court of the county where the property is located within ninety (90) days after the completion of the work, or ninety (90) days after the date materials or machinery were furnished.

How long does a claimant have to file a foreclosure lawsuit in Georgia?

Under O.C.G.A. § 44-14-361.1(a)(3), an action to recover the amount of the lien must be commenced within 365 days from the date of filing the lien for record. However, if the owner or contractor files and serves a statutory Notice to Contest Lien under § 44-14-368, the lawsuit deadline is dramatically shortened to just sixty (60) days from the filing of the contest.