Under O.C.G.A. § 44-14-361.5, if the property owner or general contractor files a Notice of Commencement with the clerk of superior court within 15 days of project start, any potential lienor not in privity of contract with the contractor must send a written Notice to Contractor within 30 days from the filing of the Notice of Commencement or 30 days from first furnishing, whichever is later.
Under O.C.G.A. § 44-14-361.1(a)(2), a Claim of Lien must be filed and recorded in the office of the clerk of superior court of the county where the property is located within 90 days after the completion of work or final furnishing of materials. Within 2 business days of filing, a copy must be sent to the owner by certified mail.