Georgia Code § 44-14 Materialmen Lien Auditor

Under O.C.G.A. § 44-14-361 et seq., when a property owner records a Notice of Commencement, remote subcontractors and suppliers must serve a statutory Notice to Contractor within 30 days of first furnishing to maintain lien rights against the real property.

Georgia Statutory Deadlines Calendar Matrix
Click audit to generate calendar...
Georgia Lien Status
Notice to Contractor Deadline (§ 44-14-361.5)
--
Strict 30 calendar days from first work
Record Claim of Lien Deadline (§ 44-14-361.1)
--
Strict 90 calendar days from final work
Lawsuit / Commencement of Action Deadline
--
395 days from recording (unless contested)
Georgia Strict Compliance Rules
  • Notice of Filing: Claimant must send copy of Claim of Lien to owner by registered/certified mail within 2 business days of recording (§ 44-14-361.1(a)(2)).
  • Notice of Commencement of Action: Must file Notice of Commencement of Lien Action with clerk of superior court within 30 days after filing lawsuit.