Under Georgia law (O.C.G.A. § 44-14-366, amended 2021), executing an Interim or Final Waiver and Release unconditionally extinguishes lien rights unless an Affidavit of Nonpayment is recorded within 90 days.
Strict 90-day statutory window under GA law
Georgia Lien Right Status
Affidavit of Nonpayment Window
42 Days Left
Must file with Superior Court Clerk before Day 90
Lien Exposure
$68,500
Breach of Contract
Preserved (SB 315)
Statutory Deemed Paid Date:Day 90 Post-Signing
Owner Notice Obligation:Serve within 7 days of filing
Mechanic's Lien Rights:ACTIVE & PROTECTABLE
Georgia SB 315 Fix: Under the 2021 legislative amendment, failure to file an Affidavit of Nonpayment only waives mechanics lien and bond rights — it NO LONGER waives breach of contract claims!