Audit Florida construction Notice of Commencement statutory windows. An NOC triggers priority for all mechanics liens. Making payments after NOC expiration or prior to recording exposes owners to paying twice for the same work ("improper payments").
Under Florida law: (1) An NOC is void if construction is not commenced within 90 days of recording, (2) Unless a longer duration is stated in the document, an NOC automatically expires one (1) year after recording, (3) Making progress payments to the general contractor after the NOC has expired without recording a valid new or amended NOC constitutes an "improper payment," leaving the owner vulnerable to paying twice if unpaid subcontractors file liens, (4) An owner terminating an NOC early under § 713.132 must serve notice on all lienors who served a Notice to Owner (NTO) at least 30 days prior to recording the Notice of Termination.