Florida Construction Lien Law § 713.06 Notice to Owner (NTO) Auditor

Audit statutory perfection deadlines under Florida Construction Lien Law (Fla. Stat. Chapter 713): mandatory 45-day Notice to Owner (NTO) deadline from first furnishing of labor, services, or materials (Fla. Stat. § 713.06(2)(a)), strict 90-day Claim of Lien recording window from final furnishing (Fla. Stat. § 713.08(5)), 15-day service of recorded lien on owner, and statutory foreclosure lawsuit limitations (1 year from recording, or expedited 60-day deadline upon Clerk's Notice of Contest of Lien under § 713.22).

1. Florida Project Timeline & Lien Status
Claimants NOT in direct privity must serve a Notice to Owner (NTO) within 45 days.
Statutory NTO deadline is 45 calendar days from first work/delivery (Fla. Stat. § 713.06(2)(a)).
Claim of Lien must be recorded within 90 calendar days of final furnishing (§ 713.08(5)).
Copy of recorded lien must be served on owner within 15 days (§ 713.08(4)(c)).
2. Florida Statutory Perfection Audit
Lien Validity Status
Awaiting Audit
Configure construction timeline milestones to audit statutory lien validity.
Florida Statutory Milestone Statutory Deadline Audit Result
Notice to Owner (NTO) (§ 713.06) 45 Days from 1st Furnishing Pending
Claim of Lien Recording (§ 713.08) 90 Days from Final Furnishing Pending
Lien Service on Owner (§ 713.08) 15 Days from Recording Pending
Foreclosure Lawsuit Limitation 1 Year vs 60-Day Notice of Contest Pending
Lien Enforceability Assessment Strict Compliance Rule Pending
Florida Strict Construction: Florida Construction Lien Law is in derogation of common law and is strictly construed by Florida courts. Missing the 45-day NTO window or 90-day recording window by even one single day completely voids the lien and exposes the claimant to owner attorney fees for fraudulent or invalid liens.