Audit statutory perfection deadlines under Florida Construction Lien Law (Fla. Stat. Chapter 713): mandatory 45-day Notice to Owner (NTO) deadline from first furnishing of labor, services, or materials (Fla. Stat. § 713.06(2)(a)), strict 90-day Claim of Lien recording window from final furnishing (Fla. Stat. § 713.08(5)), 15-day service of recorded lien on owner, and statutory foreclosure lawsuit limitations (1 year from recording, or expedited 60-day deadline upon Clerk's Notice of Contest of Lien under § 713.22).
| Florida Statutory Milestone | Statutory Deadline | Audit Result |
|---|---|---|
| Notice to Owner (NTO) (§ 713.06) | 45 Days from 1st Furnishing | Pending |
| Claim of Lien Recording (§ 713.08) | 90 Days from Final Furnishing | Pending |
| Lien Service on Owner (§ 713.08) | 15 Days from Recording | Pending |
| Foreclosure Lawsuit Limitation | 1 Year vs 60-Day Notice of Contest | Pending |
| Lien Enforceability Assessment | Strict Compliance Rule | Pending |