Florida Statutes Ch. 713 NTO & Lien Auditor

Under Florida Statutes § 713.06, claimants not in direct contractual privity with the owner (subcontractors, sub-subcontractors, material suppliers) must serve a statutory Notice to Owner (NTO) within strict timelines or completely forfeit lien rights.

Florida Ch. 713 Statutory Calendar Deadlines
Click calculate to generate deadline matrix...
Lien Rights Protection Matrix
Notice to Owner (NTO) Deadline (§ 713.06(2)(a))
--
Strict 45 calendar days from first work
Recording Claim of Lien Deadline (§ 713.08(5))
--
Strict 90 calendar days from final work
Foreclosure Lawsuit Filing Deadline
--
1 Year from recording (unless accelerated)
Strict Compliance Rule
  • Fatal Timing: Serving an NTO on day 46 is completely fatal to lien rights in Florida courts; doctrine of substantial compliance does not apply.
  • 15-Day Service Rule: Claim of Lien must be served on owner within 15 calendar days of recording in public records.
  • Contractor Final Affidavit: Prime contractors must serve Final Payment Affidavit at least 5 days prior to filing foreclosure suit.