ASCE Technical Guidelines • Contractual Risk Allocation

Geotechnical Baseline Report (GBR) DSC Auditor

Audit civil excavation, deep foundation, and tunneling conditions against the contractual Geotechnical Baseline Report. Establish clear mathematical proof of a Type I Differing Site Condition (DSC) when field conditions exceed baseline metrics.

Baseline Specifications vs Field Encounter

Unconfined Compressive Strength.
Lab core testing results.
Shallower = Higher dewatering costs.
Cubic Yards
$

Type I DSC Determination & Quantum Claim

TYPE I DSC CONFIRMED: Field conditions exceeded contractual GBR baseline.
Rock UCS Exceedance +116.7%
Total Equitable Claim $517,500
Contractual Baseline Metric: 12,000 psi (Medium Hard Rock)
Encountered Field Metric: 26,000 psi (Extremely Hard Granite)
Groundwater Table Deviation: 13 Ft Shallower than Baseline
Contractual Disclaimer Enforceability: GBR Governs (Disclaimers Void)

Contractor Recovery Entitlement: 100% Compensable DSC
ASCE GBR Guidelines & Claim Strategy:
Auditing subsurface data...
The American Society of Civil Engineers (ASCE) GBR Protocol
Why GBRs Eliminate Litigation:

Traditional factual boring logs (GDR) invite endless disputes over what was "reasonably foreseeable." The GBR establishes clear, binding contractual baselines. If field conditions are more severe than the baseline, the contractor is paid an equitable adjustment without needing to prove engineer negligence!

Order of Precedence:

Well-drafted contracts establish that the GBR takes contractual precedence over factual boring logs, drawings, and site-visit disclaimer clauses, neutralizing broad owner disclaimers of subsurface accuracy.

Notice Before Disturbance:

Virtually all Differing Site Conditions clauses (FAR 52.236-2 and EJCDC C-700) mandate that notice must be given promptly before the conditions are disturbed, allowing the owner to inspect and take verification core samples.