US Construction Unforeseen Subsurface Conditions (Type I & II) Claim Generator

Analyze differing site conditions claims under Federal FAR 52.236-2, AIA A201 § 3.7.4, EJCDC, and State DOT specs. Calculate direct excavation rework, idle equipment standby, and extended overhead delays, and generate an immediate notice letter.


Frequently Asked Questions

Under Federal FAR 52.236-2 and standard construction contracts, a Type I condition exists when actual subsurface physical conditions differ materially from the conditions indicated in the contract documents (e.g., encountering solid granite rock where boring logs showed soft clay). A Type II condition exists when an unknown physical condition of an unusual nature is encountered that differs materially from conditions ordinarily encountered in that type of work (e.g., finding unrecorded buried historical catacombs or uncharted toxic munitions).

Nearly all construction contracts (FAR 52.236-2, AIA A201 § 3.7.4, EJCDC C-700) explicitly state that notice must be given 'before such conditions are disturbed.' If a contractor excavates, hauls away, or covers the unforeseen condition before the owner has an opportunity to inspect and verify it, courts often rule that the claim is waived because the owner was prejudiced in its ability to investigate.

No. Federal courts and state supreme courts consistently rule that generic clauses requiring the contractor to 'thoroughly inspect the site prior to bidding' do NOT override a Differing Site Conditions clause. Bidders are not required to conduct independent exploratory deep drillings or geophysical surveys when the owner has provided official geotechnical boring reports.

A contractor can recover: (1) direct extra labor, materials, and equipment required to overcome the condition (e.g., rock ripping, wellpoint dewatering); (2) idle standby costs for workers and equipment shut down during the delay; (3) extended field overhead (general conditions); and (4) a reasonable markup for overhead and profit, along with a compensable time extension to prevent liquidated damages.