Calculates allowable contractor cost recovery and settlement compensation when an owner or government agency terminates a construction contract for convenience. Models direct job costs, work-in-progress overhead and profit, subcontractor settlement liabilities, unexpired lease commitments, and statutory bars against claiming anticipated profits on unperformed work.
Originating during the Civil War to prevent government waste at the cessation of hostilities, the Termination for Convenience doctrine permits the government or private owner to terminate a contract without cause without committing a breach. Under federal procurement law (FAR Part 49 and FAR 52.249-2), the contractor's recovery is strictly limited by regulation.
Prior to 2017, AIA A201 § 14.4.3 allowed the contractor to recover 'reasonable overhead and profit on the Work not executed.' In the 2017 revision, this was completely deleted and replaced with a 'termination fee, if any, set forth in the Agreement,' eliminating automatic entitlement to unearned profits unless expressly bargained for in writing.
Under federal law (Torncello v. United States, 681 F.2d 756), a termination for convenience executed in bad faith, with intent to injure, or representing an abuse of discretion constitutes a common law breach of contract, entitling the contractor to full expectation damages including lost profits on unperformed work.
If government audit reveals that the contractor would have suffered a loss had the entire contract been completed, no profit is allowed on incurred costs, and incurred costs are reduced proportionally by the estimated loss ratio.
Under FAR 52.249-2(e), the contractor must submit a final termination settlement proposal to the Contracting Officer within one year from the effective date of termination, unless extended in writing. Failure to submit within one year forfeits the right to negotiate and permits the agency to determine compensation unilaterally.