US Construction Termination for Convenience Settlement Costs Calculator

Calculate contractor termination for convenience claims under Federal FAR 52.249-2 and AIA Document A201-2017 § 14.4. Model completed work balances, subcontractor cancellation fees, demobilization, unamortized mobilization, and settlement preparation costs.


Frequently Asked Questions

When an owner terminates a contract for convenience, the contractor is entitled to: (1) payment for all work satisfactorily executed up to the termination date; (2) costs of terminating and settling subcontracts and purchase orders (including restocking and cancellation fees); (3) demobilization and site cleanup costs; (4) unamortized upfront mobilization, bond, and insurance costs; and (5) professional legal and accounting fees incurred in preparing the settlement proposal.

Under federal FAR 52.249-2 and public contracts, anticipatory profits on unperformed work are strictly prohibited as a matter of law. Under private contracts (like AIA A201-2017 § 14.4.3), the contractor cannot recover unearned profit unless the parties specifically agreed to an express 'Termination Fee' in the contract agreement.

Under FAR 52.249-2(e), a government contractor must submit its final termination settlement proposal within one (1) year from the effective date of termination. Failure to submit within the 1-year window can result in forfeiture of the right to recover settlement costs.

Yes! Under FAR 31.205-42 (Termination Costs) and standard construction law, reasonable accounting, legal, and clerical expenses incurred for the preparation and presentation of the settlement proposal are expressly allowable and reimbursable as indirect settlement expenses.