Contractors have both contractual rights (under standard AIA A201 § 9.7 or ConsensusDocs) and statutory rights under state Prompt Payment Acts. If an undisputed progress payment is past due, statutory notice must be given prior to lawful suspension of labor and equipment.
Under California Civil Code §§ 8830-8848, an original contractor must give a 10-day notice of intent to stop work to the owner. The notice must also be posted conspicuously at the job site and sent to the construction lender.
Under Texas Property Code § 28.009, if a contractor is not paid undisputed amounts within 35 days of invoice (or 7 days from owner payment for subs), they may suspend performance 10 days after serving written notice. The contractor is legally protected against delay damages and entitled to demobilization/remobilization costs.
Yes. If a contractor halts work without complying with statutory notice days, without a bona fide payment default, or where bona fide good-faith dispute exists, the owner may terminate for default, claim breach of contract, and backcharge completion costs.