Audits subcontractor pass-through claims sponsored by prime contractors against project owners under the historic Severin Doctrine. Evaluates liquidation agreements, conditional liability mechanics, and fatal non-recourse/exculpatory clause traps that extinguish the prime contractor's liability to the subcontractor and thereby legally extinguish the claim against the owner.
Because subcontractors lack contractual privity with the government or private project owner, a subcontractor cannot directly sue the owner for breach of contract or equitable adjustment. Instead, the claim must be 'passed through' and sponsored by the prime contractor.
In Severin v. United States (99 Ct. Cl. 435), the U.S. Court of Claims established the doctrine that: A prime contractor cannot sponsor a subcontractor's claim against the owner if the prime contractor has been completely released from liability to the subcontractor for that claim. If the prime contractor is not liable to the subcontractor, the prime contractor has suffered no damage, and therefore has no claim to assert against the owner.
To avoid the fatal trap of the Severin doctrine, modern construction practice developed Liquidation Agreements. As reaffirmed in J.L. Simmons Co. v. United States (304 F.2d 886) and Interstate Contracting Corp. v. City of Dallas (135 S.W.3d 605):
Yes. Under federal contracting law, the government bears the burden of establishing that the prime contractor was completely, unconditionally, and irrevocably exculpated from all liability to the subcontractor. Any conditional liability defeats the Severin defense.
Under 41 U.S.C. § 7103(b), for claims over $100,000, the prime contractor must personally certify in good faith that the claim is accurate, made with complete belief in its validity, and reflects the amount for which the government is liable. Sponsoring a subcontractor claim without independent prime verification can subject the prime to False Claims Act penalties.
Yes. Under Cal. Pub. Cont. Code § 9204(d)(5), on California public works, a prime contractor is statutorily required upon written request to present a subcontractor's claim to the public agency within 45 days, unless the claim is clearly fraudulent.