Analyze exculpatory delay clauses under state statutory prohibitions (Cal. Pub. Cont. Code § 7102), evaluate active interference and bad faith exceptions, and compute delay damages using the Eichleay Formula.
In California public contracts, any clause that attempts to limit the contractor's recovery for owner-caused delay is void as against public policy if the delay is unreasonable under the circumstances and not within the contemplation of the parties.
Under New York law (Corinno Civetta Constr. v. City of New York, 67 N.Y.2d 297), a clause is unenforceable if delays were caused by: (1) bad faith or gross negligence; (2) uncontemplated delays; (3) breach of fundamental obligation; or (4) active interference.
In Zachry Constr. Corp. v. Port of Houston (449 S.W.3d 98), the Texas Supreme Court held that exculpatory clauses cannot shield an owner from delay damages caused by its own intentional misconduct, fraud, or arbitrary interference.